Description

Overview
Sector Energy
Focus area Renewable energy (unspecified)
Type of action Project
Scope National
Stage Under development
Submitted to UNFCCC registry Yes
Start of initiative 2013
Financing and support details
Financing status Seeking financing
Total cost
(no data)
Financing requested EUR 55 mln
Financing received to-date
(no data)
Principal source of financing Not known
Principal type of financing Not known
Capacity building required No
Technology transfer required No
Additional information
Proponent(s) Public Enterprise Electric Power Industry of Serbia
International funder(s)
(no data)
Organization providing technical support
(no data)
Contact Vladimir Djordjevic, Exe. Dir. for Renewables

Balkanska 13, Belgrade +381 11 2024 600 vladimir.djordjevic@eps.rs

Dragan Vukotic Vojvode Stepe 412, Belgrade +381 11 3952 349 dragan.vukotic@eps.rs

Objective:

The NAMA involves construction of 9 new small hydropower plants (HPP) throughout Serbia. The total capacity of 9HPP is 30.40 MW with possible electricity production of 108.3 GWh/year. All of the electricity generated will be supplied to the Serbian electricity grid, which is currently composed mostly of carbon-intensive lignite-fired thermal power plants. The NAMA will contribute to climate change mitigation as the hydro power as renewable energy source does not emit any greenhouse gases (GHGs) during operation, and reduces GHGs that would otherwise be emitted from grid-connected power plants in the absence of the mitigation action.

Activities: (2013 - 2017)
The project consists of two phases:

Phase I: Construction of 6 small scale hydropower plants in the area of existing hydro facilities

Phase II: Construction of 3 small scale hydropower plants in the new locations.

Impact and MRV

No Data Available.png
Cumulative GHG reductions: 4.1 MtCO2e
Mitigative capacity:

No information has been provided on mitigative capacity

Co-benefits:

Social: Creation of local employment opportunities.
Economic: Information has not been provided
Environmental: Reduction of impact on environment, and awareness raising among general public about clean energy

MRV Framework:
No MRV plan has been defined